NJ data center emitted staggering amounts of air pollution for nearly a year before regulators intervened
DataOne, the Microsoft-linked New Jersey datacenter recently hit with a  for running unpermitted generators, emitted large amounts of health-harming air pollution for nearly a year before state regulators stepped in, according to public records obtained by .
The Vineland facilityâs 62 gas-fired generators became public in August after  found them operating without permits. The New Jersey Department of Environmental Protection fined the company over the fleet, but didnât disclose how long the generators had been operating, nor how much air pollution they had released into the surrounding community over the past year.Â
Floodlight sent technical data about the generators â obtained through public records requests â to two experts to calculate the siteâs emissions.Â
âOur best estimate is that the generators emitted about 140 tons of NOx,â said Xiaomeng Jin, an assistant professor at Rutgers Department of Environmental Sciences. Her analysis would rank DataOne in the stateâs top five NOx polluters of 2025, per EPA data.
NOx is a dangerous group of smog-producing gases , Â and even . Itâs âthe most important air pollutant in the U.S. that affects most people,â Jin said.
Longtime Vineland resident Tiffany Leone-Vespa lives about a mile from the data center and said the noise from the generators sounds like an airplane in the back of her house.Â
âWhat health problems might I face in the future? Because I've been exposed to all of that. My kids have been exposed to it,â she said.
The siteâs potential NOx emissions are even larger, according to Jin and Bruce Buckheit â a former EPA air enforcement division chief. Both concluded that at full use, DataOneâs fleet could emit more than 1,500 tons of NOx per year. That is nearly twice the amount that the Linden Cogeneration gas-fired power plant, New Jerseyâs largest NOx emitter, is allowed to emit.Â
Operating the generators âresults in very high levels of air pollution,â said Buckheit.Â
New Jersey labels any facility capable of emitting more than 25 tons of NOx per year a âmajor sourceâ and DataOneâs potential emissions are âwell overâ that limit, Buckheit said. Obtaining a major source permit requires extensive environmental reviews, best available pollution controls and public comment periods â all before construction can even begin.Â
That didnât happen at DataOne, despite the operation being capable of emitting more than half the NOx put out by New Jerseyâs entire power sector.
âThat is basically offsetting some of the air quality improvements [regulators] have achieved for decades,â Jin said.Â
DataOne did not respond to Floodlightâs emissions analysis. Instead, its spokesperson sent the same statement as they did in response to NJDEP's decision to fine them, saying the company is "transitioning to low-emission, quiet fuel cells as part of the siteâs permanent power solution and have the necessary approvals in place for this solution.âÂ
The company disagrees with NJDEPâs determination and had argued the generators did not require permits â but plans to apply for them now.
A Microsoft spokesperson wrote that "we expect our suppliers and partners to meet all applicable legal and regulatory obligationsâ and the company was working with DataOne âto support their completion of the facility's transition to its permanent long-term power solution.â
In press releases, New Jersey regulators said the tractor-trailer-sized generators were detected during a July 29, 2026, site inspection but not during an earlier visit in December. However, the fleet was there to find, according to a letter DataOne later sent to NJDEP.
The letter, obtained by Floodlight through a public records request, notes that the generators first began to arrive in July 2025. Sixteen generators started operating in October 2025, with another 16 brought online in early February. By June, all 62 had been fired up.
By the time state inspectors noticed them, the unpermitted fleet had collectively run for more than 46,000 hours in total, according to the letter.
âHow did 62 generators get installed and operated and nobody did anything until now? That blows me away,â Leone-Vespa said. âClearly somebody wasn't doing their job.âÂ
A spokesperson for NJDEP declined to comment.
For many Vineland residents, confirmation that DataOneâs generators have been running for nearly a year is a bittersweet vindication. Locals have reported strange noises emanating from the facility for months, with more than 100 noise complaints submitted to the Cumberland County Department of Health since March, according to records obtained by Floodlight. Many of the complaints list generators as the suspected source.Â
âThey're just running these monster generators. And they think, by right, they have every ability to do so at the expense of anyone else,â said local flower farmer Michael Atkinson.
Atkinson's family has been farming a patch of land beside the data center for more than 70 years. He said DataOne is âone of the richest and worst neighbors that I have ever had to deal with in my entire life.â
During a Vineland , DataOne CEO Charles-Antoine Beyney told residents that his data center would be âpolluting less than a farm.âÂ
Born in Bordeaux, Beyney told the crowd, âIâm too French to just kill my lungs, the lungs of your kids and all the community around us.âÂ
Beyney confirmed during that speech that DataOne was running generators, and he said NJDEP was aware â claiming the agency had been at the site that same morning and was âon us big time.â
While the generators may have evaded state regulators for a year, local officials knew about them for much longer.
A City of Vineland  noted that âPhase 1 generators are onlineâ in early February. And in May, a Cumberland County Health Department inspector responding to a noise complaint visited the site and reported that the source of the noise appeared to be two generators, âpossibly more.âÂ
The inspector noted that the noise âexceeded a nighttime violation.âÂ
As part of the record fine levied against DataOne, the state is mandating the company apply for and obtain the required permits or cease operations, but is allowing them 45 days to do so, according to a NJDEP spokesperson.
During that time, regulators are allowing the facility to continue running the generators â which are capable of emitting more than four tons of NOx in nearby neighborhoods each day.
âI just don't understand how this is being allowed,â Leone-Vespa said. She hopes independent air monitoring can help protect her community in the future. Until then, she has little faith in New Jersey regulators to watch out for them.
âIt's like they don't care about the residents.â